Tiny house foundations – my cheap and simple solution

Pictured is me building my tiny house foundations
Pictured is a sketch of typical pier foundations
Pier and pad foundation sketch

There are loads of ways I could have built the foundations of the tiny house. However, for a long time I have been drawn to the idea of building a house raised up on piers.

I think I got the idea from the Walter Segal building method which uses simple concrete pads (600mm square) and timber posts (piers) as foundations for timber framed houses.

The advantages of this method are as follows:

  1. Uses less concrete than strip or raft foundations (so is cheaper and has lower environmental impact).
  2. No need for earth-moving machines and extensive groundwork to level the site (again saves money).
  3. Easy for the self builder (just some holes to dig for the pads).
  4. Raises the house above the ground (so good ventilation of floor and no dampness).
  5. Space under floor can be used to route plumbing and electrical cables.

I chose to use six piers, one at each corner and one in the middle of each of the longer sides.

Calculations

You’re probably ‘supposed’ to get a structural engineer or architect (or some other expert) to design foundations based on soil type.

Well, I didn’t do that but I did satisfy myself that my own design wasn’t complete madness.

I actually did have some information on the soil type from a study that was done for drainage purposes. The test hole nearest to the tiny house showed that, at a depth of 0.4m, the soil was “grave limoneuse”. As far as I understand, this literally means “gravel and silt”. Silty soils apparently have less than 10% clay. My land was certainly free draining (as I would observe during some thunderstorms) which I guess wouldn’t be the case if it did contain a lot of clay.

I found some information online which indicated the load bearing capacity of different soils. The french term for this is “taux de travail”, represented by the letter q.

The worst clay soil has a q value of 0.3 bars and the best limestone soil has a q value of 45 bars.

In between these extremes were, for example, silt (1-3 bars), sand/gravel (6-9 bars) .

So, I made the conservative assumption that my silt and gravel soil wasn’t great and had a q value of only 1 bar.

Diameter of Piers

Searching the internet, I found some guidance on calculating foundation dimensions. I can’t remember the source, or be sure it’s 100% correct, but here is how I did it anyway.

I used a reference figure of 250kg per m2 of floor are as the load placed on the foundations of a timber framed house (this may or may not be correct!).

My floor area was 17.28m2, so the total load was 4,320kg.

As there were six piers, I assumed that each carries 1/6 of the 4,320kg load i.e. 720kg.

I had read that concrete of 15cm diameter can, in theory, support 22,000kg. So if I used a similar diameter for my foundation piers, they should cope with the 720kg load easily enough.

It is possible that the load on the piers is more than 720kg due to the extra weight of the hempcrete insulation. But even if it was twice as much (1440kg), it should still be OK.

Size of concrete pads

For the concrete pads, I did the following calculation. As previously discussed, I took the q value to be 1 bar and the load on each pad to be 1440kg.

Pictured and hand written foundation calculations
Foundation pad size calculation

So I ended up with a pad size of 50cm x 50cm which is reassuringly close to the 60cm x 60cm square pads used by Walter Segal for his buildings.

Building the pads and piers

Firstly, I used a square wooden frame to mark the ground with bright pink marker spray.

Pictured is a square wooden frame for marking foundation pads
Marking foundation pads using a square wooden frame

I then dug the holes by hand to a depth of about 50cm (to get below the frost line). This was surprisingly difficult because it had been hot for some weeks and the ground was bone dry and hard. So I had to use a pick to loosen the earth and then scrape out the ‘dust’ with the spade and shovel. A few tree roots in some of holes didn’t help. Nevertheless, after a day of digging they were complete.

The pads were cast in concrete at least 20cm thick and reinforced with 10mm steel rebar.

The next question was how to make the piers?

Pictured is a concrete foundation pier
Filled concrete foundation pier

I thought about using bricks or shuttered concrete using cardboard tubes or plywood formwork. In the end I used hollow concrete blocks that were, effectively, permanent shuttering. The blocks are designed for the pillars of garden gates. Various sizes are available and I went for 20cm x 20cm (exterior dimensions). They were built up to a slightly higher level than required and the finished level marked using a laser. The tops were cut off using an angle grinder. They were then filled with concrete and some more 10mm steel rebar.

Pictured is how I fixed the house floor beam to the foundations
Fixing the floor beam to the foundations

While the concrete was still wet, the floor beams were laid on top of the piers and joined at the corners using heavy duty angle brackets. Another angle bracket was used to allow ‘spikes’ of 10mm rebar to connect the beam with the wet concrete in the piers. In effect the floor beam would be pegged to the piers and couldn’t move around laterally. There seemed to be no point in bolting the floor beam down. The weight of the building would surely be enough to keep it in place, Wizard of Oz style tornadoes notwithstanding!

I didn’t use any damp proof material between the timber and the piers as the finished cladding would overhang the concrete and shield the tops from the weather.

The total cost for the foundations was probably just over €100 euros. The blocks cost €56, the cement about €25, the rebar about €24 plus a fairly small amount of sand and gravel.

Pictured below are all six piers with the floor beam installed on top ready for the floor joists.

Pictured are concrete piers with timber floor beam
Concrete piers with floor beam in place

First things first – making a gravel driveway

Pictured is a mini digger in use
Pictured is my building plot prior to the driveway being built
Building plot before the driveway was made

This was one of the first things that had to be done and possibly the job that I was least looking forward to. Not only had I never made a driveway before, I knew that if I screwed it up it would introduce delays right at the start of the build. I didn’t have much time to spare.

However, it was part of the planning conditions that I included parking for two cars. It was also necessary for the building project that I have safe access for trucks onto the site in order to deliver materials.

So I had to make a driveway/parking area of about 50m2 and it had to be quick and cheap. At the same time, I needed to dig a trench for the water pipe (from the property boundary to somewhere a bit closer to the build).

I knew I didn’t need anything fancy and I wasn’t bothered about a few weeds springing up at a later date. Rustic was absolutely fine with me.

Design

From information gleaned from French building forums I reckoned the driveway should be about 25cm deep. I would be using Calcaire (Limestone) graded at 0-30mm. The quantity needed worked out about 12m3 or approximately 18 tonnes (two truckloads).

Excavation

The mini digger was hired for the weekend but was actually delivered on Friday afternoon, so I had en extra evening to figure out how it worked.

I took it very slowly and experimented with the various controls. One thing I didn’t know was how to change the bucket (two different sizes were supplied). Luckily a friend of mine came around on Saturday morning to show me how it was done and give me some driving tips.

Excavating the drive was a slow process. The fact that we were in the middle of a heatwave meant that the ground was hard and dusty. So it was more ‘scrape, scrape’ rather than ‘dig, dig’. It was also so hot (35 deg) that, after several hours, concentrating became difficult and it became even harder to coordinate the controls.

Nevertheless, by the end of the weekend I had shifted enough soil. This was just as well, as I had the delivery of stone arriving on Monday morning.

Rake, rake, rake

I was concerned that the stone delivery from the tipper truck would spill out onto the road, blocking it, and that I wouldn’t be able to rake it out fast enough to clear the obstruction!

As it turned out the stones did spill out slightly into the road but not enough to block it. With the help of my kids we started barrowing, shoveling and raking the stones out. The picture below shows it halfway through the process.

Pictured is my gravel driveway being built
Driveway stones, 2nd load

It took a while but eventually all the stones were spread out and it seemed like the quantity was about right. I didn’t compact the stones using a vibrating plate as I didn’t want to spend the time or money on it. Instead I would rely on vehicles and the weather to do that job. Likewise I didn’t lay a top dressing of finer gravel, the 30mm limestone looked ok and was easy enough to drive and walk on.

Pictured is the finished driveway
The finished driveway

The total cost of the driveway was €1,235 (€478 for the digger hire and €757 for the stone).

I don’t know exactly how much a contractor would have charged for the job. From various website it seems that something like €50 per square metre is a realistic price (total cost €2500).

Even if I had used geotextile membrane, a compactor and a top dressing, it is likely that I would still have saved about €1,000 by doing the work myself.